Toledo's Martin Luther King, Jr. Bridge has been subject to short closings lately. It's about to be out of commission
for a longer period. The structure is in the process of getting a complete overhaul, and will close today so the central drawbridge section can be replaced. People will have an easy time remembering when they'll be able to cross it again. It opens two days after Valentine's Day.
The Cherry Street Bridge, as it was first known, was built between 1910 and 1914, at a cost of one million dollars. That may seem like pocket change for building a bridge these days, but back then it was the most expensive public improvement project in Toledo's history. Like most expensive public projects, the building of the bridge was controversial. There were a lot of people who thought spending a million dollars on a bridge was just plain crazy. They lost the argument, but managed to get a few corners cut in the budget. For example, the best part of the design, four tall, column-like towers were never built. Two of them were to sit at either end of the drawbridge to house the lift mechanism. That's a shame. I've seen the plans and they were impressive. Everyone likes to save money, but no one liked the plain wooden sheds that were built instead. It was a long while before they gave way to the current structures, which are an improvement, but nowhere near as nice as the towers.
One other interesting thing about the building of this bridge, it was constructed right next to the old bridge it replaced. No traffic problems there.